Metro Power

Pakistan
Demonstrating the viability of wind power projects in Pakistan
Sector
Power/Energy
Total PIDG Commitment
USD 18.5m
Related SDG Goals
Project Overview
Investee CompanyMetro Power Company Limited
SectorPower and energy (Wind)
CountryPakistan
Total Project CostUSD 117.3m
PIDG Commitment
  • EquityUSD 18.5m 
Dates of PIDG involvement
  • 20142017 
Challenge

As a politically fragile state, few international investors are capable of managing the risks of capital-intensive infrastructure projects in Pakistan. However, Pakistan is in critical need of investment in infrastructure in general, and in renewable energy in particular. In 2014, the power capacity shortfall in Pakistan was more than 5,000 MW- about one-third of the total demand on the system. Load shedding was persistent, with the public being forced to stay without power for more than 9 to 10 hours per day in some cities and around 16 to 18 hours per day in many rural areas.  

Solution

In 2012, PIDG – through InfraCo – began developing the Metro Wind Power and Gul Ahmed Wind Power Projects jointly with local sponsors, the Alimohamed Family (Metro Wind Power) and Gul Ahmed Energy (Gul Ahmed Wind Power). InfraCo provided development stage expertise and capital to complete the development of the projects and secure debt financing from international and local lenders. Together with further funding support InfraCo enabled the project to reach financial close in Q4 2014. The project commenced commercial operations in Q3 2016. 

The project contributes 50MW of renewable wind energy generation capacity and helps address the country’s power capacity deficit, together with reducing Pakistan’s exposure to high cost and insecurity of fuel imports, as well as reduce carbon emissions. InfraCo successfully divested its interest in the project to the private sector in September 2017. 

Impact

People

c. 69,265 households or 346,325 people were expected to benefit from improved services through the project. 

Planet

The project is expected to reduce carbon emissions by about 92,500 tonnes per annum. 

Wider economy

The project was expected to improve general economic activity directly through greater electricity supply stability in the region. 

Market transformation

The project was one of the first to receive funding from MDBs and DFIs in Pakistan at its time. 